Answer:
$281,612
Step-by-step explanation:
Plane Operating Cost = Fixed cost + (Variable cost per unit1 × q1) + (Variable cost per unit 2 × q2)
Plane Operating Cost = $40,190 + ($2709*88) + ($10 * 303)
Plane Operating Cost = $40,190 + $238,392 + $3,030
Plane Operating Cost = $281,612
So, the plane operating costs in the planning budget for August would be $281,612