Answer:
$2,344,356
Step-by-step explanation:
Given the above information,
June production :
Planned sales + ending inventory - beginning inventory
= (27,000 + 70 - 490) units
= 26,580 units
Total direct labor hour required for production
= 26,580 units × 4.2
= 111,636 labor hour
Cost of production
= Total direct labor hour × rate per hour
= 111,636 × $21
= $2,344,356