Two teams working together can finish a job is 8 days. If the first team works alone for two days and the second team works alone for 5 days, 5/8 of the total work remains. How many days would it take each team to finish the work alone.

1 Answer

7 votes

Answer:

Hey! I believe your answer would be:

12 days, and 24 days.

Hope this helped!

Explanation: