Answer:
See below
Step-by-step explanation:
First, we have to compute the actual price
Actual price = Actual cost of material purchased × Actual material purchased
= $201,500 ÷ 10,200 metres
= $19.75
Therefore,
Material price variance
= Actual quantity × (Actual price - Standard price)
= 10,200 × ($19.75 - $19)
= 10,200 × $0.75
= $7,650 favourable