Answer:
The predetermined overhead rate for the recently completed year would be $25.66
Step-by-step explanation:
The predetermined overhead rate is computed as;
= Total estimated manufacturing overhead / estimated direct labor
Where;
Total estimated manufacturing overhead = Estimated total fixed manufacturing overhead + estimated variable manufacturing overhead rate × estimated labor hours
= $1,196,840 + $2.82 × 52,400
= $1,196,840 + $147,768
= $1,344,608
Therefore,
Predetermined rate = $1,344,608 / 52,400 hours
Predetermined rate = $25.66