Answer:
Total cost per day= $1,892.72
Step-by-step explanation:
Giving the following information:
Foreman= 26.09 per hour
Cement finisher= 29.3 per hour
Labor= 24.45 per hour
Equipment operator= 34.5 per hour
To calculate the total cost for one day of work, we need to multiply the hourly rate by the total number of hours.
Total cost per day= 26.09*8 + 29.3*8 + (24.45*6)*8 + 34.5*8
Total cost per day= $1,892.72