A company makes a product using two materials, one of which is interchangeable with a third material. The standards for producing one 200-pound batch are presented below. The last 200-pound batch was produced using 185 pounds of M and 210 pounds of O. The price of M was $0.03 per pound and the actual price of O was $0.10.

Material Standard Quantity (lbs) Standard Cost/lb. Total Cost
O 0 $0.10 $0
H 125 0.08 10.00
M 75 0.02
1.50 200 $11.50
Is the material mix variance favorable or unfavorable

User Ovanes
by
8.0k points

1 Answer

8 votes

Answer:

The material mix variance unfavorable.

Step-by-step explanation:

This can be determined using the following 3 steps:

Step 1: Calculation of the total Standard Cost of Actual Mix of the 3 materials

Standard Cost of Actual Mix of material O = Units of material O used * Standard cost of material O = 210 * $0.10 = $21

Standard Cost of Actual Mix of material H = Units of material H used * Standard cost of material H = 0 * $0.08 = $0

Standard Cost of Actual Mix of material M = Units of material M used * Standard cost of material M = 185 * $0.02 = $3.79

Total Standard Cost of Actual Mix of the three materials = Standard Cost of Actual Mix of material O + Standard Cost of Actual Mix of material H + Standard Cost of Actual Mix of material M = $21 + $0 + $3.79 = $24.70

Step 2: Calculation of the total Standard Cost of Standard Mix of the 3 materials

Standard Cost of Standard Mix of material O = Standard Units of material O * Standard cost of material O = 0 * $0.10 = $0

Standard Cost of Standard Mix of material H = Standard Units of material H * Standard cost of material H = 125 * $0.08 = $10

Standard Cost of Standard Mix of material M = Standard Units of material M * Standard cost of material M = 75 * $0.02 = $1.50

Standard Cost of Standard Mix of the three materials = Standard Cost of Standard Mix of material O + Standard Cost of Standard Mix of material H + Standard Cost of Standard Mix of material M = $0 + $10 + $1.50 = $11.50

Step 3: Calculation of material mix variance

Material mix variance = Total Standard Cost of Actual Mix of the three materials - Standard Cost of Standard Mix of the three materials = $24.70 - $11.50 = $13.20

Since the Total Standard Cost of Actual Mix of the three materials is greater than Standard Cost of Standard Mix of the three materials (i.e. by $13.20), this implies that the material mix variance unfavorable.

User Alex Woolford
by
8.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories