24.8k views
3 votes
He5-B9q Company operates two departments, the handling department and the packaging department. During May, the handling department reported the following information: % complete % complete units DM conversion work in process, May 1 113,000 33% 48% units started during May 201,000 work in process, May 31 169,000 74% 28% The cost of beginning work in process and the costs added during May were as follows: DM Conversion work in process, May 1 $ 94,128 $ 59,904 costs added during May $418,986 $372,816 Calculate the total cost of the 113,000 units in beginning work in process using the FIFO process costing method.

1 Answer

2 votes

Answer:

Total cost of the 113,000 units in beginning work in process is $282,628.58.

Step-by-step explanation:

Note: The data in the question are merged together. They are therefore sorted before answering question by presenting the complete question as follows:

He5-B9q Company operates two departments, the handling department and the packaging department. During May, the handling department reported the following information:

% complete % complete

units DM conversion

work in process, May 1 113,000 33% 48%

units started during May 201,000

work in process, May 31 169,000 74% 28%

The cost of beginning work in process and the costs added during May were as follows:

DM Conversion

work in process, May 1 $94,128 $59,904

costs added during May $418,986 $372,816

Calculate the total cost of the 113,000 units in beginning work in process using the FIFO process costing method.

Explanation of the answer is now provided as follows:

This total cost of the 113,000 units in beginning work in process using the FIFO process costing method calculated using the following 4 steps:

Step 1: Calculation of equivalent units

Particulars DM Conversion

To complete work in process, May 1:

113000*(1-33%) 75,710

113000*(1-48%) 58,760

Units started and completed (w.1) 88,000 88,000

Work in process, May 31:

169000*74% 125,060

169000*28% 47,320

Equivalent units 288,770 194,080

Step 2: Calculation of cost per equivalent units

Cost per Equivalent unit = Costs incurred during May / Equivalent units ....... (1)

Using equation (1), we have:

DM Cost per Equivalent unit = $418,986 / 288,770 = $1.45

Conversion Cost per Equivalent unit = $288,770 / 194,080 = $1.92

Step 3: Calculation of Total Cost to complete work in process, May 1

Cost to complete work in process, May 1 = To complete work in process, May 1 * Cost per Equivalent unit ................ (2)

Using equation (1), we have:

DM Cost to complete work in process, May 1 = 75,710.00 * $1.45 = $109,850.16

Conversion Cost to complete work in process, May 1 = 58,760 * $1.92 = $112,874.42

Total Cost to complete work in process, May 1 = DM Cost to complete work in process, May 1 + Conversion Cost to complete work in process, May 1 = $109,850.16 + $112,874.42 + $222,724.58

Step 4: Calculation of Total cost of the 113,000 units in beginning work in process

Total cost of the 113,000 units in beginning work in process = Work in process, May 1 + Cost to complete work in process, May 1 = $59,904 + $222,724.58 + $282,628.58

Workings:

w.1: Units started and completed = Units started during May - Work in process, May 1 = 201,000 - 113,000 = 88,000

User TNguyen
by
5.7k points