Answer:
$1.70
Step-by-step explanation:
Note : Quick Step Company uses direct labor hours as the allocation base
therefore,
Predetermined manufacturing overhead rate = Budgeted overheads ÷ Budgeted Activity
= $425,800 ÷ 250,200
= $1.70
Therefore, the Predetermined manufacturing overhead rate would be $1.70