Answer:
36
Explanation:
We assume that time is inversely proportional to the number of workers. So increasing the number of workers by a factor of 121/99 = 11/9 will decrease the number of days by a factor of 9/11.
(9/11)(44 days) = 36 days
It will take 36 days to complete the construction with 121 workers.