517,179 views
26 votes
26 votes
4 workers can dig 4 holes in 4 hours, how long will it take to dig 6 holes with 2 workers

User Andrey Solovyov
by
3.0k points

2 Answers

22 votes
22 votes

Answer:

12 hours

Explanation:

4 workers can dig 4 holes in hours=4

1 worker ,, ,, 4 ,, ,, ,, =4×4=16

1 ,, ,, ,, 1 hole ,, ,, =16÷4=4

2 ,, ,, ,, 1 ,, ,, ,, =4÷2=2

2 ,, ,, ,, 6 holes ,, ,, =2×6=12

User Murali Kurapati
by
2.8k points
21 votes
21 votes

Answer:

12 hours

Explanation:

each worker digs a hole and takes 4 hours doing so

2 workers dig 3 holes each, 3*4=12, 12 hours

User Vulwsztyn
by
2.5k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.