Answer:
EcoScape Company
a. EcoScape should use a job-order costing method because each job is different.
b. The overhead rate is $8.70.
c. The average actual wage rate is $10
d. The cost will be equal to $3,911.
Step-by-step explanation:
a) Data and Calculations:
Estimated Actual
Number of direct labor hours 6,560 6,150
Direct labor cost $59,040 $61,500
Overhead cost $57,072 $57,810
Overhead rate = $57,072/6,560 = $8.70
Average actual wage rate = $61,500/6,150 = $10
The cost of an installation that takes $3,350 of direct materials and 30 direct labor hours will be:
Direct materials $3,350
Direct labor cost 300 (30 * $10)
Overhead cost 261 (30 * $8.70)
Total costs $3,911