Answer:
$30.59
Step-by-step explanation:
Note that the FIFO method is used for this question
Equivalent Units
Materials = 5,200 x 100 % + 300 x 100 % = 5,500
Conversion Costs = 400 x 55 % + 5,200 x 100 % + 300 x 35 % = 5,525
Total Costs
Materials = $25,200
Conversion Costs = $143,700
Cost per Equivalent unit
Materials = $25,200/5,500 = $4.58
Conversion Costs = $143,700/5,525 = $26.01
Total Cost = $4.58 + $26.01 = $30.59
Conclusion
The cost of completing a unit during the current period was $30.59