Answer:
under-applied overheads is $1,340
Step-by-step explanation:
Note : I have attached the full question/similar as an image below.
Actual Overheads = $594,960
Applied Overheads = $594,960 / 22,200 x 22,150 = $593,620
Since,
Actual Overheads > Applied Overheads, overheads have been under-applied.
Amount of under-applied overheads is $1,340 ($594,960 - $593,620).