The top-down method for estimating project time and cost that uses weighted variables based on major parameters and is frequently used in the development of software is known as the ____________ method. Multiple Choice ratio consensus learning curves apportion function point

User Manigandand
by
2.9k points

1 Answer

19 votes
19 votes

Answer:

function point

Step-by-step explanation:

The top-down method for estimating project time and cost that uses weighted variables based on major parameters and is frequently used in the development of software is known as the FUNCTION POINT METHOD

This is because, in the computer technology industry, the Function Point method is a type of strategy that is utilized in measuring software development projects.

It is considered to be a weighted macro variable such as volume of inputs, the volume of outputs, the volume of inquiries, volume of data files, and volume of interfaces.