Answer:
b.direct materials of $47,248
Direct labor=$57,965
Variable Utilities=8,758
Supervisor salaries $14,600
Step-by-step explanation:
Computation of flexible budget
FLEXIBLE BUDGET
Direct materials
$41,000/10,500*12,100
Direct materials= $47,248
Direct labor=50,300/10500*12100
Direct labor=$57,965
Variable Utilities
=7600/10500*12100
Variable Utilities=8,758
Supervisor salaries $14,600 Fixed cost