Answer:
Lap Corporation
The cost of the units completed and transferred out of the department was:
= $825,000.
Step-by-step explanation:
a) Data and Calculations:
Beginning work in process inventory = 80,000 units
Degree of completion = 100% materials and 25% conversion
Cost of beginning work in process = $226,000
Units transferred out = 150,000
Materials Conversion Total
Costs per equivalent unit $2 $3.50
Cost of units transferred out $300,000 $525,000 $825,000
= (150,000 * $2) (150,000 * $3.50)