During a risk brainstorming session a team member identifies a risk. This particular risk does not seem to belong to any of the categories in you Risk Breakdown Structure (RBS). How should you respond

User StatguyUser
by
2.7k points

1 Answer

13 votes
13 votes

Answer:

Record it in the risk register, discuss potential responses and make a note to update the RBS.

Step-by-step explanation:

Risk management is the process by which the management of an organisation identifies, assessed, and controls threats that may affect the company's capital or earnings.

The risks can be as a result of natural disasters, management error, financial uncertainty, or accidents.

In the given instance if a risk is not on any of the categories in you Risk Breakdown Structure (RBS), there is need to record it in the risk register, discuss potential responses and make a note to update the RBS.