Answer and Explanation:
The computation of the variable overhead spending and efficiency variances is given below:
Actual VOH AH ×SVOR SH × SVOR
222816 57200 × 3.75 = 214500 60000 × 3.75 = 225000
8316 10500
Hence, 8316 is unfavorable
And, 10,500 should be favorable