392,649 views
38 votes
38 votes
You are considering two mutually exclusive projects. Project A costs $3.6 million, has a required return of 14.5 percent, and an IRR of 14.3 percent. Project B costs $4.1 million, has a required return of 16 percent, and an IRR of 15.6 percent. Which project(s) should be accepted

User Jason Shultz
by
2.4k points

1 Answer

19 votes
19 votes

Answer:

Neither

Step-by-step explanation:

The internal rate of return is a capital budgeting method that is used to determine the profitability of a project.

Internal rate of return is the discount rate that equates the after-tax cash flows from an investment to the amount invested

The decision rule when using the internal rate of return is to undertake the project if the internal rate of return is greater than the required return of the project. If this is not met, the project should be rejected.

If choosing between multiple projects, the decision rule is to choose the projects with the highest internal rate of return. This is because that project would be the most profitable.

Neither of the project should be selected because the IRR of both projects is less than their required returns

User ItsLex
by
2.6k points