Answer:
70,200 units
Step-by-step explanation:
Calculation to determine the budgeted materials purchases for April
Using this formula
Budgeted material needed for april=April budgeted production calls +
+ (Ending inventory*Ending inventory percentage)- Beginning inventory
Let plug in the formula
Budgeted material needed for april= 71,000 + (67,000*20%) -14,200
Budgeted material needed for april= 71,000 + 13,400-14,200
Budgeted material needed for april= 70,200 units
Therefore the budgeted materials purchases for April is 70,200 units