Answer:
Machine setups= $33.7 per setup
Step-by-step explanation:
Giving the following information:
Estimated Expected Activity Activity Cost Pools Activity Measures Overhead Cost Product Z1 Product Z8 Total
Machine setups setups 40,440 500 700 1,200
To calculate the activity rate, we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Machine setups= 40,440 / 1,200
Machine setups= $33.7 per setup