Answer: Setup time is dependent on the number of units subsequently produced.
Step-by-step explanation:
It should be noted that a setup is a required activity and a set of activities. A setup time is also referred to as the changeover time.
The statement that "Setup time is dependent on the number of units subsequently produced" is false. The setup time refers to the interval that is needed to adjust the machine settings in order to make it ready to process a job. The setup time isn't dependent on the number of units that's subsequently manufactured.