Answer:
Total cost= $10,160
Step-by-step explanation:
First, we need to calculate the predetermined overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (306,000/85,000) + 6
Predetermined manufacturing overhead rate= $9.6
Now, we can allocate overhead to Job P951, and calculate the total cost:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 9.6*100
Allocated MOH=$960
Total cost= 700 + 8,500 + 960
Total cost= $10,160