Answer:
NO
Step-by-step explanation:
Discounted payback calculates the amount of time it takes to recover the amount invested in a project from it cumulative discounted cash flows
For the machine to be accepted, the total amount invested should be recovered in three years or less
Amount recovered = - cost of the project + discounted value of the cash flow
Amount recovered in year 1 = -10,000 + (4000 / 1.12) = -6,428.57
Amount recovered in year 2= -6,428.57 - (4000/ 1.12^2) = -3239.74
Amount recovered in year 3= -3239.74 + (4000/ 1.12^3) = -392.62
the project would not be accepted because the amount invested would not be recovered within 3 years