Answer:
The pounds of materials should have been
= 630,000 pounds.
The machine hours should have been
= 84,000 hours.
Step-by-step explanation:
a) Data and Calculations:
Standard materials per package = 3 pounds
Standard machine hours per package = 0.40 hours
Actual production units during August = 210,000 units
Actual materials used = 440,000 pounds
Actual machine hours used = 85,000 hours
Standard materials = 630,000 pounds (210,000 * 3)
Standard machine hours = 84,000 hours (210,000 * 0.40)