XYZ Company estimates the amount of materials handling overhead cost that should be allocated to the company's two products using the data that are given below: Wall Mirrors Specialty Windows Total expected units produced 9,000 6,000 Total expected material moves 400 100 Expected direct labor-hours per unit 7 5 The total materials handling cost for the year is expected to be $6,800. The materials handling cost is allocated based on the number of materials moves. What is the total materials handling cost allocated to the specialty windows

User Canned Man
by
2.7k points

1 Answer

18 votes
18 votes

Answer: $2,720

Step-by-step explanation:

Total materials handling cost for specialty windows = Proportion of total units * Total materials handling cost

Proportion of total units = Specialty units / (Specialty windows + Wall mirrors)

= 6,000 / (6,000 + 9,000)

= 0.4

Total material handling cost for specialty windows = 0.4 * 6,800

= $2,720