The purpose of rough cut capacity planning is to: Select one: a. place a time fence around the MPS. b. determine a production schedule that offers a rough order of magnitude. c. cut excess capacity from the MPS. d. assess the feasibility of the MPS. e. govern the length of the execution cycle.

User Bhavik
by
2.6k points

1 Answer

9 votes
9 votes

Answer:

The answer is "Option d".

Step-by-step explanation:

To compute the estimated work on master capacity planning, the objective of basic resource allocation is utilized. It is then contrasted to a proven ability that enhances organizational MPS feasibility.

It verifies that you have enough ability at your disposal that satisfy the needs of your master's programs. It is a tool in long-term production scheduling for marketing and production to accomplish the ratio of the capacity required and accessible and to manage changes in the plan and/or looking.