493,193 views
37 votes
37 votes
You are considering an investment project with an internal rate of return of 8.7 percent, a net present value of $393, and a payback period of 2.44 years. Which one of the following is correct given this information?

A. The discount rate used to compute the net present value is equal to the Internal rate of return.
B. The discounted payback period will be less than 2.44 years.
C. The required payback period must be greater than 2.44 years.
D. The discount rate used in computing the net present value was less than 8.7 percent.
E. This project should be rejected based on the net present value.

User Pierre Arlaud
by
2.9k points

2 Answers

8 votes
8 votes

Answer:

D). The discount rate used in computing the net present value was less than 8.7 percent.

Step-by-step explanation:

'Net Present Value' is described as the 'difference that exists between existing values of cash inflows, as well as, cash outflows for a particular time period.' This assists in evaluating the profitability of an investment and make worthy decisions regarding investment.

As per the details provided, the discount rate considered for estimating the Net Present Value of the investment had been lesser than 8.7% which shows that the Net Present Value in positive i.e. $ 393. However, the investment project is not beneficial at all rather it may cause losses because the required return rate is 9.5% which is actually lesser and therefore, the project would prove incompetent and it must be rejected at once. Thus, option D is the correct answer.

User Thomas Ahle
by
2.8k points
10 votes
10 votes

Answer:

Hence the correct option is d) The discount rate used in computing the net present value was less than 8.7 percent.

Step-by-step explanation:

As the discount rate increases, the present value decreases, and also at IRR the present value is zero, thus the answer is:-

d) The discount rate used in computing the net present value was less than 8.7 percent

User GrantByrne
by
2.5k points