Langler, Inc., is evaluating two capital projects. Langler has a capital budget of $50 million. Project P has an internal rate of return of 24% and a net present value of $5 million. Project Q has an internal rate of return of 18% and a net present value of $12 million. Project P will cost $15 million, and Project Q will cost $48 million. Based on this information, Langler should accept:

User Klumsy
by
7.7k points

1 Answer

14 votes

Answer: Project Q

Step-by-step explanation:

If the company can accept only one project, they should accept Project Q because it has a higher net present value than Project P. This is because a higher Net Present value takes precedence to IRR as it discounts cashflows at the company's cost of capital and is already adjusted for cost.

With the company budget at $50 million, accepting Project Q which costs $48 million means that they will be unable to accept Project P. That is fine because Project Q as earlier mentioned, provides a higher NPV.

User Ruveena
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories