A contractor construct to build a house in 30 days. He employed 10 men to build the house. After 20 days. They completed only 1 /3 of the total work. How many more men will be required to finish the remaining work within due time?

User Fogmeister
by
2.7k points

1 Answer

14 votes
14 votes

Answer:

30

Explanation:

First, we can say that because the men do 1/3 of the work in 20 days,

for 10 men:

20 days = 1/3 total work

Because we need the house built in 30 days, and 20 days have already passed, we only have 30-20=10 days left. Furthermore, 20/2=10, so in our equation of 20 days = 1/3 total work, we can divide both sides by 2 to get

10 days = 1/6 total work

The amount of work we need to get done in 10 days is (all of it) - (1/3 of total work) = 1 - 1/3 = 2/3 = 4/6

Since 10 men can do 1/6 of the work in 10 days, 10*4 =40 men can do 1/6 * 4 = 4/6 of the work in 10 days. This is the amount of work that needs to get done. Therefore, the contractor needs 40 (total workers) - 10 (current workers) = 30 new workers to finish the remaining work in due time