Answer:
Allocation rate Machining= $50 per machine hour
Step-by-step explanation:
Giving the following information:
Estimated Machining cost= $4,000,000
Estimated Number of machine hours= 80,000
To calculate the allocation rate for the Machining department, we need to use the following formula:
Allocation rate Machining= total estimated costs for the period/ total amount of allocation base
Allocation rate Machining= 4,000,000 / 80,000
Allocation rate Machining= $50 per machine hour