Job order versus Process Costing Which of the following industries would typically use job order costing, and which would typically use process costing? Steel manufacturing Business consulting Web designer Computer chip manufacturing Candy making Designer clothes manufacturing

User Saravana
by
2.5k points

1 Answer

16 votes
16 votes

Answer:

Job order versus Process Costing

Industries using job order costing:

Business consulting

Web designer

Designer clothes manufacturing

Industries using process costing:

Steel manufacturing

Computer chip manufacturing

Candy making

Step-by-step explanation:

In job order costing, the manufacturer tracks its prime costs to individual products or jobs. This means that the costs of each job can be computed separately because costs are traced to each job. Under process costing, the prime costs are tracked to the department or process or batch, and not to individual products or jobs.