The time to complete a project varies inversely

with the number of employees. If 3 people can
complete the project in 7 days, how long will it
take 5 people?
O 4.2
O 21
O 11.7
O 2.1

1 Answer

6 votes

Answer:

4.2

Explanation:

T = K/N

K= TN

= 3×7

K= 21

Therefore the time required for 5 employees can be calculated as follows

T= 21/5

= 4.2