Units to be Assigned Costs Kraus Steel Company has two departments, Casting and Rolling. In the Rolling Department, ingots from the Casting Department are rolled into steel sheet. The Rolling Department received 4,000 tons from the Casting Department in October. During October, the Rolling Department completed 3,900 tons, including 200 tons of work in process on October 1. The ending work in process inventory on October 31 was 300 tons. How many tons were started and completed during October? fill in the blank 1 tons

User DrSvanHay
by
3.1k points

1 Answer

27 votes
27 votes

Answer:

the no of tons started and completed is 3700

Step-by-step explanation:

The computation of the no of tons started and completed is given below:

Units Completed = Beginning Work in Process Units Completed + Units started and Completed during October

3,900 = 200 + Units started and Completed during October

So,

Units started and Completed during October = 3,700

Hence, the no of tons started and completed is 3700