Answer:
No.
Explanation:
Given that :
Maximum accepted Ramp slope = 1/12
A new ramp with :
Height range = 5 feets
Horizontal stretch = 50 feets
Th slope = Rise / Run = Height range / horizontal stretch = 5 / 50 = 1 / 10
1 / 10 > 1 / 12
This means the new ramp's slope is greater than than the maximum slope specification ; and hence not acceptable