Answer:
$33.80 per hour
Step-by-step explanation:
The computation of the predetermined overhead rate is shown below:
= Estimated manufacturing overhead ÷ machine hours
= ($71,000 + $12,100 + $54,900 + $14,000 + $17,000) ÷ (5,000 machine hours)
= $169,000 ÷ 5,000 machine hours
= $33.80 per hour