Answer:
Underapplied overhead= $1,200
Step-by-step explanation:
Giving the following information:
Actual manufacturing overhead costs incurred $35,000
Manufacturing overhead allocated to jobs 33,800
To calculate the under/over allocation, we need to use the following formula:
Under/over applied overhead= real overhead - allocated overhead
Under/over applied overhead= 35,000 - 33,800
Underapplied overhead= $1,200