Answer:
JAN FEB MAR APR
Average monthly productivity 2.36 1.8 1.75 2.34
(units per hour)
Step-by-step explanation:
a) Data and Calculations:
JAN FEB MAR APR
Units Produced 2300 1800 2800 3000
Hours per Machine 325 200 400 320
Number of Machines 3 5 4 4
Total machine hours 975 1,000 1,600 1,280
Average monthly productivity
(units per hour) 2.36 1.8 1.75 2.34
Productivity per hour = Units produced/Total machine hours used