Answer:
$996,267.41
Step-by-step explanation:
The Net Present Value of Alpha`s project can be determined by using the CFj Function of a Financial Calculator as follows :
- $400,000 CF0
$325,000 CF1
$500,000 CF2
$400,000 CF3
$475,000 CF4
I/YR = 8%
Then, SHIFT NPV gives $996,267.41