Answer:
The answer is "5.5 and 90.90%"
Step-by-step explanation:
For point 1:
To calculate the speed from fast mode, its run time without enhancement should be worked out. Designers are aware of which two selves are implicated throughout the accelerated project planning: the empty (
) and the increased stages (
).
Although not enhanced, this would take almost as long (
) and for the combine to give phase; even so, the increased phase would've been 10 times longer, as well as
. Thus the corresponding total speed without enhancement is
Its overall speed is:
For point 2:
We re-connect these figures in Amdahl's Law throughout order to identify how long it would take for both the initial implementation: