An example of fast tracking a project schedule would be to overlap the design and production phases for a design-to-production project, where the conventional approach would be to move on to construction only after completing the design phase.

a. True
b. False

User Crunchy
by
2.6k points

1 Answer

19 votes
19 votes

Answer:

a. True

Step-by-step explanation:

Project management can be defined as the process of designing, planning, developing, leading and execution of a project plan or activities using a set of skills, tools, knowledge, techniques and experience to achieve the set goals and objectives of creating a unique product or service.

Generally, projects are considered to be temporary because they usually have a start-time and an end-time to complete, execute or implement the project plan.

Furthermore, the main purpose of project management is working toward a common goal.

This ultimately implies that, project managers should ensure adequate attention and time is taken to identify, analyze and manage capital, raw materials, people, system of tasks and other resources, so as to effectively and efficiently achieve a common goal with all project stakeholders.

The fundamentals of Project Management includes;

1. Project initiation

2. Project planning

3. Project execution

4. Monitoring and controlling of the project.

5. Adapting and closure of project.

In the execution of a project, delaying a task normally affects the start or finishing time of the other tasks (successors) in a project.

The amount of time that is permitted for an activity to be delayed without delaying the early start date of any immediately following (succeeding) activities refers to the free slack or having an adverse effect on entire project.

A project schedule can be defined as a plan that comprises of the deliverables, activities and milestones with respect to a project, especially by including the intended start and finish dates.

The time for the implementation or execution of a project can be fast-tracked by a project manager.

For example, you can fast-track a design-to-production project by overlapping the design and production phases; especially by moving on to construction only after completing the design phase.