Answer:
Variable cost per unit= $0.10
Step-by-step explanation:
Giving the following information:
Cost Machine Hours
March $3,106 15,176
April 2,668 9,558
May 2,892 11,947
June 3,538 17,899
To calculate the variable cost under the high-low method, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (3,583 - 2,668) / (17,899 - 9,558)
Variable cost per unit= $0.10