The manager of a crew that installs carpeting has tracked the crew’s output over the past several
weeks, obtaining these figures:
Week Crew Size Yards Installed
1 4 96
2 3 72
3 4 92
4 2 50
5 3 69
6 2 52
Compute the labor productivity for each of the weeks. On the basis of your calculations, what can
you conclude about crew size and productivity?