Answer:
Variable cost per unit= $24
Step-by-step explanation:
Giving the following information:
Month Tickets Sold Cost
March 1,500 $ 10,000
April 2,000 $ 15,000
May 3,500 $ 19,000
June 2,500 $ 17,000
July 4,000 $ 22,000
To calculate the variable cost, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (22,000 - 10,000) / (4,000 - 3,500)
Variable cost per unit= $24