In July, a new endoscopy suite will be opened in your organization. Projections are that 80 endoscopies will be performed per day. At the same time, an electrophysiology lab will be opening, with anticipation of 8 procedures being done there per day. You have done some preliminary work sampling to determine how much time it will take to code these types of cases and arrived at 10 minutes per endoscopy and 15 minutes per EP procedure. Calculate the number of FTEs that you will need to hire to cover the additional workload. Base you calculations on a 7.5-hour workday.

User Huan Zhang
by
6.7k points

1 Answer

10 votes
So because I like getting that I used math for fun so the answer will be 12.4