By representing the budget and schedule associated with each task, the Performance Measurement Baseline (PMB) allows program managers to ___________________. Reduce overall life cycle costs Complete projects on time Compare the value of work performed to actual costs Complete comparative analyses more efficiently

User Yycking
by
2.2k points

1 Answer

26 votes
26 votes

Answer:

Option C (Compare......actual costs) is the correct alternative.

Step-by-step explanation:

  • The benchmark establishing performance measurements takes place just at beginning of the assignment to monitor the construction process.
  • Three restrictions exist, notably timeframe, scope as well as money. Benchmark employee performance simply monitors the implementation with these restrictions. This enables system management to identify discrepancies promptly.

The situation presented is not connected to other alternatives. This is the solution, therefore.