71.5k views
2 votes
A factory completes 1 production of items in 12 days.

I)In how many days 1/2 part of the production is done .

ii) How much work is completed in 9 days.​

User Jjisnow
by
8.5k points

1 Answer

5 votes

I) To determine the number of days it takes to complete half of the production, we can use the concept of proportions.

If 1 production is completed in 12 days, then 1/2 of the production would be completed in half the time.

So, (1/2) production would be completed in (1/2) * 12 = 6 days.

Therefore, it would take 6 days to complete half of the production.

ii) To calculate the amount of work completed in 9 days, we can set up a proportion using the ratio of time to production.

If 1 production is completed in 12 days, then the amount of work completed in 9 days can be calculated as:

(9 days) / (12 days) = (x work) / (1 production)

Cross-multiplying, we get:

9 * 1 = 12 * x

9 = 12x

Dividing both sides by 12:

x = 9/12

Simplifying the fraction, we get:

x = 3/4

Therefore, in 9 days, 3/4 (or 75%) of the work would be completed.

To summarize:

i) It would take 6 days to complete half of the production.

ii) In 9 days, 3/4 (or 75%) of the work would be completed.

User Jonaz
by
8.2k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories