Answer:
8 days
Explanation:
A can do a piece of work in 12 days, then A can complete 1/12 of the work in 1 day.
B can do a piece of work in 15 days, then B can complete 1/15 of the work in 1 day.
So for 3 days, A can complete 3 x 1/12 = 1/4 of the work in 3 days
when B joins A, they both complete 1/12 + 1/15 = 5/60 + 4/60 = 9/60 = 3/20 of the work in 1 day.
So the work by both A and B = 1 - 1/4 = 4/4 - 1/4 = 3/4 or 15/20
the number of days both A and B will complete: (15/20)/(3/20) = 5 days