It takes for plumbers five days to fit central heating in an office block. How long would it take ten plumbers?

User HVS
by
2.7k points

1 Answer

19 votes
19 votes

Answer:

2 days

Explanation:

It takes four plumbers five days

total labor needed

4 * 5 = 20 days

How long would it take ten plumbers?

20 / 10 = 2 days